The Causeway Bridge in Wolsingham
Repair works are due to start on The Causeway bridge in Wolsingham on Tuesday 6 May 2025 and are due to be completed in early 2026.

Wolsingham Bridge Downstream Elevation
A road closure is needed for road traffic to enable the erection, re-siting and dismantling of scaffolding to take place, as well as for waterproofing and resurfacing of the bridge deck. Pedestrian access will be maintained at all times.
The initial closure will be in place from Tuesday 6 May 2025 for approximately three weeks, with each of the further three closures taking around two weeks, the dates for these will be confirmed in due course. Throughout the closure periods, a diversion will be in place. These closures have been kept to an absolute minimum.
The remainder of the project will be completed utilising temporary traffic lights and will maintain pedestrian and traffic access over the bridge. The carriageway width during the works will be limited to 3.25m, this allows for HGV vehicles however vehicles is excess of this width will need to use the diversionary route.
We would like to thank you for your co-operation and patience during this project.
Traffic management plan
Please note that there will not be any road closures in operation during the following local events:
- TruckFest on 31 May and 1 June
- Stanhope Show on 13 and 14 September
- Wolsingham Show on 6 and 7 September
Pre-construction works
Activity | Proposed traffic management | Date | Duration |
---|---|---|---|
Principal Inspection | Temporary traffic lights | 17 March 2025 | Complete |
Detailed design | N/A | February - April 2025 | Ongoing |
Scaffold erection | Full closure required for all traffic. Pedestrian access maintained at all times. | 6 - 26 May 2025 | 3 weeks |
Construction works
Activity | Proposed traffic management | Date | Duration |
---|---|---|---|
Bridge refurbishment | Temporary traffic lights to enable vehicle and pedestrian access at all times. | 27 May 2025 - Early 2026 | To be confirmed |
Scaffold re-siting | Full closure required for all traffic. Pedestrian access maintained at all times. | Early September 2025 | 2 weeks |
Scaffold dismantling | Full closure required for all traffic. Pedestrian access maintained at all times. | Mid October 2025 | 2 weeks |
Waterproofing and resurfacing of bridge deck | Full closure required for all traffic. Pedestrian access maintained at all times. | Late October/early November 2025 | 2 weeks |
Completion | Early 2026 |