The Causeway Bridge in Wolsingham


Repair works are due to start on The Causeway bridge in Wolsingham on Tuesday 6 May 2025 and are due to be completed in early 2026.

Wolsingham Bridge Closure

Wolsingham Bridge Downstream Elevation

The Causeway bridge at Wolsingham dates back to 1894 and is located between the Causeway and Wear's Bank. The bridge requires an extensive refurbishment scheme to undertake significant repairs to age-related damage. These critical works will ensure that the bridge can be used for many years to come.

A road closure is needed for road traffic to enable the erection, re-siting and dismantling of scaffolding to take place, as well as for waterproofing and resurfacing of the bridge deck. Pedestrian access will be maintained at all times.

The initial closure will be in place from Tuesday 6 May 2025 for approximately three weeks, with each of the further three closures taking around two weeks, the dates for these will be confirmed in due course. Throughout the closure periods, a diversion will be in place. These closures have been kept to an absolute minimum.

The remainder of the project will be completed utilising temporary traffic lights and will maintain pedestrian and traffic access over the bridge. The carriageway width during the works will be limited to 3.25m, this allows for HGV vehicles however vehicles is excess of this width will need to use the diversionary route.

We would like to thank you for your co-operation and patience during this project.

Traffic management plan

Please note that there will not be any road closures in operation during the following local events:

  • TruckFest on 31 May and 1 June
  • Stanhope Show on 13 and 14 September
  • Wolsingham Show on 6 and 7 September

Pre-construction works

Swipe to see full table

Activity

Proposed traffic management 

Date

Duration

Principal InspectionTemporary traffic lights17 March 2025 Complete 
Detailed design N/AFebruary - April 2025Ongoing
Scaffold erectionFull closure required for all traffic. Pedestrian access maintained at all times.6 - 26 May 20253 weeks

Construction works

Swipe to see full table

Activity

Proposed traffic management 

Date

Duration

Bridge refurbishmentTemporary traffic lights to enable vehicle and pedestrian access at all times.27 May 2025 - Early 2026To be confirmed

Scaffold re-siting

Full closure required for all traffic. Pedestrian access maintained at all times.Early September 20252 weeks
Scaffold dismantlingFull closure required for all traffic. Pedestrian access maintained at all times.Mid October 20252 weeks
Waterproofing and resurfacing of bridge deckFull closure required for all traffic. Pedestrian access maintained at all times.Late October/early November 20252 weeks
Completion Early 2026 