A167 Newton Aycliffe upgrade
Work to deliver improvements to the A167's Central Avenue and Ricknall Lane junctions, and at the A167/A689 Rushyford roundabout is complete. We would like to thank all road users and residents for their patience while this work has been done. Minor works off the highway, including finishing landscaping, fencing and some signage work will be completed over the coming weeks.
Work started in July 2024 to provide additional road capacity in the area, and potentially allow the development of up to 1,400 new homes on the Low Copelaw site to the east of the town.
Programme of work
Swipe to see full table
Phase | Proposed traffic management | Time | Expected start | Expected end |
---|---|---|---|---|
Rushyford roundabout | Temporary traffic lights during construction | 24 hours | Complete | Complete |
Rushyford roundabout | Road resurfacing of roundabout approaches. Lane closure in operation. | Night work (7.00pm to 6.00am) | Complete | Complete |
Rushyford roundabout and St Cuthberts Way | Essential overnight road closures for resurfacing | Night work (8.00pm to 6.00am) | Complete | Complete |
Central Avenue closure | Central Avenue junction closed with A167 | 24 hours | Complete | Complete |
Ricknall Lane junction closure | Ricknall Lane junction with A167 | 24 hours | Complete | Complete |
Funding
We secured £7million from the Government's Housing Infrastructure Fund (HIF) to deliver the scheme.